Additional project information

  • Culvert beneath State Road D7 – 23.00 m
  • Siphon culvert beneath the Borza Canal – 50.00 m
  • Remetin culvert – 29.00 m
  • Contract value: €176,007.90 (excluding VAT)

Contractual deadline

12.01.2021. – 21.02.2022..